During a deck scarification and overlay project, the existing deck on Baumann Road over I-70 failed. WHKS conducted a bridge inspection and prepared Type, Size, and Location plans for the Illinois DOT for the deck replacement of the existing four-span bridge.

IMPROVING LIVES, BUILDING COMMUNITIES

Since the project was in the construction phase, WHKS reacted quickly to design the deck replacement on an accelerated design schedule, with the improvements completed within an aggressive 3-month timeframe, preventing further schedule delays and impacts to the traveling public.

SERVICES PROVIDED:

  • Bridge inspection
  • Survey
  • Type, Size, and Location
  • Traffic Management Plan
  • Final roadway and bridge plans, specifications, and estimates